Jones Inlet to East Rockaway Inlet

Long Beach Island, NY

The highly developed communities along the south shore of Long Island, NY, from Jones Inlet to East Rockaway Inlet, have experienced major flooding during storms. In 1960, Hurricane Donna forced 300 families to evacuate the area. If Donna occurred today, it would cost residents over $20 million in damages (1994 price levels). In October 2012, Super Storm Sandy severely damaged the area, causing hundreds of millions of dollars in damage. The proposed project would provide coastal storm damage risk reduction to the highly developed communities in this area.

For more information please read the project Fact Sheet or email the Project Manager.

June 2018 Update- The U.S. Army Corps of Engineers, in coordination with partnering agencies and governmental bodies, hosted public information sessions in Long Beach, NY on June 27-28, 2018 to share further details about the Long Beach project and speak directly with interested members of the public looking for further information. The presentation from the meetings can be found here. Schedule for summer work can be found below:
Pile Driving

A status and schedule for pile installation can be seen below, which is based on the contractor's latest schedule. This will be updated weekly as necessary.

  • New York (10- expected to start on 8/10)
  • Grand (9- expected to start on 8/7)
  • Lindell (8- expected to start on 8/2)
  • Washington (7- expected to start 7/30)
  • Lafayette (6-started 7/23)
  • Laurelton (5-completed)
  • Magnolia (3-completed)
  • National (4-completed)
  • Edwards (1-completed)
  • Riverside (2-completed)
  • Long Beach (17- expected to start 9/14)
  • Monroe (16- expected to start 9/11)
  • Lincoln (15- expected to start 9/6)
  • Franklin (14- expected to start 9/3)
  • Neptune (13- expected to start 8/28)
  • Sunrise (12- expected to start 8/22)
  • Executive Towers (11-expected to start 8/15)

Beach Fill

New York to Ohio (working west) July 13th - August 1st
Long Beach to New York (working west) August 2nd - September 4th
Cheltenham to Lido Townhouses (working east) September 5th- September 28th
Cheltenham to Lincoln (working west) October 1st - October 17th
Lindon to Long Beach (working west) November 7th- November 15th
Point Lookout Town Park to Lido Townhouses (working west) November 15th- November 18th
Point Lookout Town Park to the west jetty of Jones Inlet (working east) November 24th- December 21st

June 2016 Update-The U.S. Army Corps of Engineers, in coordination with partnering agencies and governmental bodies, hosted a public information sessions in Long Beach on June 28-29, 2016 to share further details about the Long Beach project and speak directly with interested members of the public looking for further information.

February 2016 Update - The following links are to downloadable PDFs of the Final version of the U.S. Army Corps of Engineers Atlantic Coast of Long Island Jones Inlet to East Rockaway Inlet Long Beach Island, New York Coastal Flood Risk Reduction Project:

Public Meeting

The U.S. Army Corps of Engineers, in coordination with partnering agencies and governmental bodies, hosted a public information session in Long Beach Thursday evening, March 6, 2014 to share further details about the proposed Long Beach project and speak directly with interested members of the public looking for further information.