The Green Brook Sub Basin is continually subject to severe and sometimes devastating flood damage. In 1999, floodwaters from Tropical Storm Floyd caused 2 deaths and approximately
$80 million in damages.

red arrow Project Area
red arrow Past Flooding Scenes
red arrow Project Planning Objectives
red arrow Recommended Plan
red arrow Environment & Mitigation
red arrow Construction Features
Click on image to show close-up view
Click on image to show close-up view
Green Brook Map - The First Construction Element
Green Brook Map - The First Construction Element
Click on image to show close-up view (1.3 MB)

Finderne Mitigation Site

WORK IN PROGRESS
The third construction element of the Green Brook Flood Control Project is Segment U Levee. This work is being constructed on the east bank of the Middle Brook in Bound Brook, New Jersey.
APRIL 2007
Residential flooding and rescue operations
Residential flooding and rescue operations
(Click on image to show close-up view)
 NJ Transit Railroad Flooded by Nor'easter
NJ Transit Railroad Flooded by Nor'easter
(Click on image to show close-up view)
APRIL 2006
Segment T Levee and Floodwall is 99% completed
Segment T Levee and Floodwall is 99% completed
(Click on image to show close-up view)
Segment T Levee and Floodwall is 99% completed
Segment T Levee and Floodwall is 99% completed
(Click on image to show close-up view)
MARCH 2006
Finderne Farms Wetlands Mitigation Project is 84% completed.  Quality Assurance Team reviewing the construction of the tributary
Finderne Farms Wetlands Mitigation Project is 84% completed.  Quality Assurance Team reviewing the construction of the tributary
(Click on image to show close-up view)
Finderne Farms Wetlands Mitigation Project is 84% completed. Quality Assurance reps inspecting construction of the nature trail
Finderne Farms Wetlands Mitigation Project is 84% completed.  Quality Assurance reps inspecting construction of the nature trail
(Click on image to show close-up view)