The work would involve the removal of approximately 151 linear feet (LF) of existing of bulkhead
and excavation of approximately 625 cubic yards (CY) from an approximately 4,664 square foot
(SF) area to expand the existing boat basin. The 481 LF of existing bulkhead would remain, and
the existing dilapidated sheet pile would be replaced as required. A new 43-foot-long bulkhead
would be installed to connect the boat basin to the existing bulkhead. Approximately 15 LF of
existing bulkhead would be removed to enlarge the opening of the existing basin and a 20-
foot-long wave break would be installed at the opening to the existing boat basin.
The work also includes the construction of a new approximately 5,392 SF boat basin with the
installation of approximately 216 LF of new bulkhead and a 16-foot-wide by 15-foot-long boat
launch. A total of approximately 1,130 CY would be excavated from a 5,392 SF area behind
the bulkhead to three feet below Mean Low Water. Approximately 60 LF of existing bulkhead
would be removed to create a new opening for boat access. A 40-foot-long and a 10-foot-long
wave break would be installed on opposite sides of the opening of the new boat basin.
A 10-foot-wide area along the existing bulkhead would be dredged to three feet below Mean
Low Water for approximately 25 CY. Approximately 260 CY of dredge and excavation material
would be placed landward of the bulkhead across four locations behind the
bulkhead totaling approximately 1,763 square feet, approximately 140 CY would be placed
below Spring High Water. The remaining 1,640 CY of dredge and excavation material would be
placed upland.