Montauk Point

 

 

MONTAUK POINT, NEW YORK, LIGHTHOUSE REVETMENT PROJECT

The U.S. Army Corps of Engineers New York District, in conjunction with the State of New York, Montauk Historical Society, New York State Office of Parks, and Town of East Hampton have completed construction of the coastal storm damage risk management project for the historic Montauk Point, NY, lighthouse complex.

Please refer to the Fact Sheet  and Placemat for more information. 

 

September 2023 Update:  The completed project was formally turned over to the Sponsor (State of New York) for required project operation and maintenance.  We thank everyone for your significant efforts and assistance on this completed project!

June 2023 Update:  All project site restoration was completed June 2023, ahead of schedule.  Formal project turnover to the Sponsor (State of New York) for operation and maintenance of the completed project will be prepared shortly.  

January 2023 Update:  All major stone work for the new revetment is now complete as of December 2022.  Project site restoration is currently underway, with project completion anticipated for Spring 2023.  Formal project turnover to the Sponsor (State of New York) for operation and maintenance of the completed project will immediately follow.  

April 2021 Update:  Public Notice for project construction information
Project construction is underway as of March 2021; overall construction will take 2 years to complete (Spring 2023).

November 2020 Update:  The Construction contract plans and specifications have been re-advertised with a new contract solicitation. Project construction is anticipated to start in early 2021, subject to an acceptable bid and award, and will take approximately 2 years to complete.

November 2019 Update:  The Construction contract plans and specification have been prepared and are now advertised for contract solicitation. Project construction is anticipated to start in mid-2020, and will take approx. 2-years to complete.

April 2017 Update: The Final Hurricane Sandy Limited Re-evaluation Report (HSLRR), Final Environmental Assessment (EA) and Final Finding of No Significant Impact (FONSI) were formally approved by the U.S. Army Corps of Engineers on 6 April 2017.  The design phase for preparation of plans and specifications for project construction was also initiated in April 2017 and is currently underway. 

 

May 2016: The U.S. Army Corps of Engineers, New York District, announces the availability of the Draft Hurricane Sandy Limited Re-evaluation Report and Draft Environmental Assessment (DEA) with Draft Finding of No Significant Impact (DFONSI) for the proposed Montauk Point, N.Y., Coastal Storm Risk Management Project and the opening of the 30-day review period for the public to submit written comments. The public comment period ends June 3, 2016.

 

See study reports to view the approved Final HSLRR & EA

 

CONTACT: 

 

Frank Verga,
Project Manager
U.S. Army Corps of Engineers, New York District
Phone: (917) 790-8212
E-mail: Frank.Verga@usace.army.mil

Programs and Project Management Division
26 Federal Plaza
New York, NY 10278-0090

 

CONGRESSIONAL DISTRICTS: NY-1

         

 

 

Project Map